Scaled Professional Scrum SPS Real Exam Questions

Jan 13,2023

Scaled Professional Scrum SPS real exam questions are the latest material in the IT market. The Scaled Professional ScrumTM (SPS) certification validates your knowledge of using the Nexus Framework as described in the Nexus Guide. SPS tests your knowledge needed to enable multiple Scrum Teams to work from a single Product Backlog to build an Integrated Increment that meets a goal. I just collected all the related SPS exam information for you to pass SPS test. 

Scaled Professional Scrum SPS Real Exam Questions

Scrum SPS Exam Details

Scrum certification SPS exam details can help you understand the test well. 
Number of questions: 40
Time Limit: 60 minutes
Passing score: 85%
Price: $250
Format: Multiple Choice, Multiple Answer, True/False

SPS Scrum Certification Exam Topics

The following are the details of Scales Professional Scrum SPS exam topics. 
Identify typical challenges in scaling, and learn principles and techniques for overcoming them
Understand how to find the scale that works best for your organization and processes, including when to reduce or “de-scale”
Experience the negative impact of cross-team dependencies on value delivery at scale
Learn how identify, visualize, minimize and remove dependencies through cross-team refinement
Learn how the Nexus framework extends and reinforces the key principles of Scrum to enable value delivery at scale
Experience the Nexus framework in action - including the events, accountabilities and artifacts
Experience techniques for organizing teams, organizing the work and running a Nexus
Learn how to deliver value across the whole Nexus instead of optimizing the work of the individual teams

Share Scrum Certification SPS Real Exam Questions

Scrum Certification SPS real exam questions are the latest version for you to test the above Scaled Professional Scrum SPS exam topics. Share some Scaled Professional Scrum SPS real exam questions below. 
1. Nexus with 3 teams have selected 4 PBIs for the upcoming Sprint. Team A will work on Item 1, Team B will work on Item 2 & 3, Team C will work on Item 4. Item 3 has a dependence on Item 2. Which PBI is the most concerning?
A. Item 3, because it cannot proceed without the completion of Item 2
B. None of the PBIs
C. Item 2, because Item 3 has dependence on it
D. All the 4 PBIs
Answer: B

2. The Nexus Team has failed to meet the Nexus Sprint Goal for two sprints in a row. What are the possible reasons for this? (Select two best answers)
A. There is technical debt in the product
B. Definition of Done has too stringent
C. Developers are struggling to integrate their work
D. Nexus Integration Team is not coordinating the work among the developers
Answer: A,C

3. Which is NOT a valid artifact in Nexus?
A. Product Backlog
B. Nexus Sprint Backlog
C. Definition of Done
D. Integrated Increment
Answer: C

4. What is the purpose of Nexus Sprint Planning? Select two best answers
A. Create a plan for upcoming Sprint
B. Ensure all teams have enough work
C. Coordinate the activities between the Scrum teams
D. Finalize the product's architecture
Answer: A,C

5. A five team Nexus is developing a purchase order application. There are several dependencies and Nexus faced a lot of challenges in managing them. How should they conduct their Nexus Sprint Planning to minimize such difficulties due to the dependencies?
A. Merge the Cross-Team refinement and Nexus Sprint Planning
B. Make the Nexus Integration Team to assign the work from the Nexus Sprint Backlog
C. Discover and document the dependencies during the cross-team refinement event and focus more on the dependencies during Nexus Sprint Planning
D. Finish the Nexus Sprint Planning only after every developer is familiar with all the dependencies
Answer: C