Certified Associate in Project Management CAPM real exam questions have been updated, which contain 1089 Q&As. The CAPM certification offers recognition to practitioners who are interested or are just starting a career in project management, as well as project team members who wish to demonstrate their project management knowledge. To prepare CAPM exam well, the following CAPM exam information and topics are valuable in your preparation.
Learn CAPM Exam Information
The CAPM recognizes your knowledge of the profession’s preeminent global standard, you’ll stand out to employers and be poised to move ahead. In real CAPM exam, there are 150 questions. Each candidate has 3 hours to complete all the questions. CAPM is online Proctored exam. Besides, you can register Certified Associate in Project Management exam at Pearson VUE test center.
Master CAPM Exam Topics
PMI CAPM exam topics cover all the following sections.
1. Introduction to Project Management (6%)
2. Project Environment (6%)
3. Role of the Project Manager (7%)
4. Project Integration Management (9%)
5. Project Scope Management (9%)
6. Project Schedule Management (9%)
7. Project Cost Management (8%)
8. Project Quality Management (7%)
9. Project Resource Management (8%)
10. Project Communication Management (10%)
11. Project Risk Management (8%)
12. Project Procurement Management (4%)
13. Project Stakeholder Management (9%)
Study CAPM Real Exam Questions
All the CAPM real exam questions can help you test the above exam topics. Share some Certified Associate in Project Management CAPM real exam questions below.
1.What is the main benefit of the lessons learned register?
A. Provides validation requirements
B. Supplies monitoring and reporting methods
C. Improves the performance of future projects
D. Documents the status of deliverables and project results
Answer: C
2.What is both an input and output of the Control Quality process and is updated as a result of this process?
A. Lessons learned register
B. Risk register
C. Enterprise environmental factors (EEFs)
D. Root cause analysis
Answer: A
3.A project manager is estimating project activities using an algorithm to calculate costs or durations.What is this technique called?
A. Analogous estimating
B. Three-point estimating
C. Parametric estimating
D. Bottom-up estimating
Answer: C
4.In which Project Cost Management process is work performance data included?
A. Plan Cost Management
B. Estimate Costs
C. Determine Budget
D. Control Costs
Answer: D
5.A project manager is talking with their manager about the advantages of following a particular project management approach.What component of the project manager's sphere of influence does this represent?
A. The project
B. The organization
C. Professional discipline
D. Across disciplines
Answer: C