The following C_TS422_2020 questions are part of our SAP C_TS422_2020 real exam questions full version. There are 148 in our C_TS422_2020 full version. All of our C_TS422_2020 real exam questions can guarantee you success in the first attempt. If you fail C_TS422_2020 exam with our SAP C_TS422_2020 real exam questions, you will get full payment fee refund. Want to practice and study full verion of C_TS422_2020 real exam questions? Go now!

 Get C_TS422_2020 Full Version

SAP C_TS422_2020 Exam Actual Questions

The questions for C_TS422_2020 were last updated on Feb 21,2025 .

Viewing page 1 out of 4 pages.

Viewing questions 1 out of 20 questions

Question#1

Your quality department detects a deviation in a raw material batch. Unfortunately, this batch has already been used in production .
How can you identify all affected finished goods stocks?

A. Use the material staging report.
B. Use the batch information cockpit.
C. Use the material where-used report.
D. Use batch determination.

Question#2

Why would you use phantom assemblies? Note: There are 3 correct answers to this question.

A. To make the assignment of components easier
B. To simplify the structure of bills of material
C. To reduce the number of changes required in bills of material
D. To increase the number of planning levels
E. To reduce the number of material masters

Question#3

Mode selection is one of the scheduling options available in Advanced Planning in SAP S/4HANA. When can you use mode selection?
A. When multiple planned orders exists in one resource
B. When alternate resourcesare used within one operation
C. When multiple production versions are maintained for one product
D. When multiple operations are maintained for one product

A. B

Question#4

In your plant, MRP is activated .
Which options do you have to exclude a material from the MRP run? Note: There are 2 correct answers to this question.

A. Use a specific material status.
B. Use a specific MRP controller.
C. Use a specific material group
D. Use a specific MRP type.

Question#5

Which actions does the system perform by default when you save a confirmation for a finished product in repetitive manufacturing? Note: There are 3 correct answers to this question.

A. Archiving of documents for assembly scrap
B. Posting of production costs to the production cost collector
C. Reduction of associated capacity requirements
D. Material staging for next order in sequence
E. Posting of goods receipt for the product