The following C_TS412_1909 questions are part of our SAP C_TS412_1909 real exam questions full version. There are 112 in our C_TS412_1909 full version. All of our C_TS412_1909 real exam questions can guarantee you success in the first attempt. If you fail C_TS412_1909 exam with our SAP C_TS412_1909 real exam questions, you will get full payment fee refund. Want to practice and study full verion of C_TS412_1909 real exam questions? Go now!

 Get C_TS412_1909 Full Version

SAP C_TS412_1909 Exam Actual Questions

The questions for C_TS412_1909 were last updated on Feb 21,2025 .

Viewing page 1 out of 4 pages.

Viewing questions 1 out of 20 questions

Question#1

Which of the following statements are true? Choose the correct answers. There are 2 correct answers to this question.

A. You can map a project using only one WBS or one network.
B. You can also represent a project using a WBS and one or more networks.
C. You can create a project based on a Activity.
D. You cannot use the characteristics of both the structures (WBS and Networks) together to represent a project.

Question#2

Dates
You have a project with a network, material and milestone. You want to plan an activity to start two days after its predecessor.
How can you do that? Note: there are 2 correct answers for this question.

A. Use an offset of two days for the relationship of both activities.
B. Use an offset of two days for milestone date.
C. Use an offset of two days for the requirement date of the material component
D. Calculate the start date of the activity and set the constraint "Must start on" accordingly.

Question#3

Resources
How can you define external task in your project. Note: there are 2 correct answers for this question.

A. Assign a purchase order for external processing to the project definition.
B. Create an external activity in a network.
C. Create a service milestone.
D. Create a service activity in a network.

Question#4

Resources
You Want assign milestone to WBS element? For what can you use these milestone.

A. To create standard network
B. To start workflow task.
C. For trend analysis.
D. To set an actual finish date for WBS element-

Question#5

Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct answers to this question

A. Material master
B. Network activity
C. WBS element
D. BOM item